●Construction Scope:
●Procurement, installation, and commissioning for a complete set of compressor.
●Design and construction of compressed air pipelines in the workshop.
●Inspection procedures for pipelines and pressure vessels.
●Pressure testing and cleaning of pipelines
●As-built drawings
Centrifuges: 400 cubic meters -4 units
Centralized control system, high-pressure cabinets(4 units) low-pressure cabinets, soft start and other post-processing equipment (4sets)
Cooling tower: 1500 cubic meters (1 unit)
Water pumps: 800 cubic meters (4 units)